Restoration Plan
|
The
Society’s initial task was to obtain estimates of restoration costs from
professional restoration contractors.
As a result of these estimates, a restoration plan has been developed. |
|
Stabilization
Phase I - Complete foundation
replacement. Requires elevating the
building, excavation work, poured footing and rebuilding stone foundation
………………………………………………...$55,000
Phase II – While building is
elevated, install vapor barrier and new wood
sill on new foundation; attach floor
joists
…………………………………………………$16,000
Phase III – Repair and replace
structural members of Northeast corner, requiring new corner post. Remove plywood flooring and replace with pine
boards. Strengthen existing floor joists
…………………………………………….…..$21,000
Phase IV – Remove existing plywood
wall paneling and repair existing plastered wall. Replace rotten window sills. Replace rotten exterior wood siding.
Paint, primer and finish coat, exterior walls
………………………………………………….$48,000
Total ……………………………… $140,000

1/31/2007 WP/kh