Restoration Plan
|
The
Society’s initial task was to obtain estimates of restoration costs from
professional restoration contractors.
As a result of these estimates, a restoration plan has been developed. |
|
Stabilization
Phase I - Complete
foundation replacement. Requires
elevating the building, excavation work, poured footing and rebuilding stone
foundation
………………………………………………...$78,000
Phase II – While building
is elevated, install vapor barrier and new wood
sill on new foundation; attach floor
joists
…………………………………………………$28,000
Phase III – Repair and
replace structural members of Northeast corner, requiring new corner post. Remove plywood flooring and replace with pine
boards. Strengthen existing floor joists
…………………………………………….…..$38,000
Phase IV – Remove existing
plywood wall paneling and repair existing plastered wall. Replace rotten window sills. Replace rotten exterior wood siding.
Paint, primer and finish coat, exterior walls
………………………………………………….$73,000
Phase V – Provide for
handicap accessibility
………………………………………………….
$10,000
Total
……………………………… $227,000